Edgewood Stadium Renovation Project Progress Gallery:
Updated 6/17/22
Updated 6/9/22
Phase 1 construction which includes field turf, track, and light replacement is scheduled to begin Tuesday, May 10, 2022. The completion date is estimated to be August 1, 2022.
During the time between May 10, 2022, and Aug 1, 2022, no one will be permitted inside the gates of the stadium other than construction teams. We apologize for the inconvenience this may cause but we are sure you understand the importance of the safety of students, family, staff, and the community during this project.
The field renovation project is a joint effort between Edgewood City Schools, corporate sponsorship, and individual donors.
At this point, money has been allotted to complete Phase 1 of the project. We thank everyone who has contributed.
Phase 2 will consist of much-needed concession stand expansion, additional locker rooms, asphalt, additional equipment storage, a new entry gate, and fencing.
To find out how to make a corporate or individual donation, please go to the link below and complete the request for information.